Friday, November 15, 2024
HomeCanadian NewsTrans Mountain undertaking prices ’moderately and justifiably incurred’

Trans Mountain undertaking prices ’moderately and justifiably incurred’

Facebook
Twitter
Pinterest
WhatsApp


Article content material

The corporate constructing the Trans Mountain pipeline growth has submitted proof to assist its declare that oil corporations should pay extra in tolls in mild of the pipeline undertaking’s mounting prices.

In a brand new regulatory submitting, Trans Mountain Corp. calls the elevated capital prices of the pipeline growth undertaking — which have ballooned to a projected $30.9 billion from a 2017 estimate of $7.4 billion — “moderately and justifiably incurred.”

Article content material

The Crown company stated in written proof submitted Friday to the Canada Power Regulator that the undertaking has been affected by “extraordinary” components that embody evolving compliance necessities, Indigenous lodging, stakeholder engagement and compensation necessities, excessive climate and the COVID-19 pandemic.

“Over the past a number of many years, Canadians have positioned higher emphasis on environmental and regulatory oversight, rights of Indigenous peoples, mitigation of socio-economic impacts and landowner rights when constructing a serious undertaking,” Trans Mountain Corp. stated in its submitting.

“These necessities elevated prices of the undertaking.”

The Trans Mountain pipeline, which was purchased by the federal authorities in 2018, is Canada’s solely oil pipeline to the West Coast. Its practically full growth undertaking will enhance the pipeline’s capability by 590,000 barrels per day to a complete of 890,000 barrels per day, enhancing entry to export markets for Canadian oil corporations.

Crown company, oil corporations disputing over tolls

However Trans Mountain Corp. and its oil firm prospects are at present engaged in a dispute over tolls, the time period for the charges the pipeline firm will cost to ship oil on the expanded pipeline.

Article content material

Trans Mountain needs to cost oil corporations a benchmark toll that’s practically twice the quantity of a 2017 estimate, because it seeks to recoup among the growth’s spiralling capital prices.

Associated Tales

It has already been granted permission by the Canada Power Regulator to cost that greater toll as soon as the pipeline growth is operational, however solely on an interim foundation till the regulator makes a ultimate resolution.

In its submitting, Trans Mountain factors out that 70 per cent of the undertaking’s price overruns can be borne by the pipeline firm and may have no have an effect on tolls.

The remaining third, which works out to roughly $9.1 billion, is taken into account “uncapped prices” which enhance tolls in accordance with a formulation agreed to by shippers and accredited by the regulator greater than a decade in the past.

Value overruns anticipated to have an effect on returns on funding

The Crown company additionally says that due to the undertaking’s price overruns, it expects solely “modest returns” on its funding within the first few years of the expanded pipeline’s operation. It says that any toll stage under what Trans Mountain has utilized for “may affect Trans Mountain’s means to fulfill its monetary obligations.”

In a separate regulatory submitting final week, Trans Mountain Corp. reapplied for a beforehand rejected request for a pipeline variance. The corporate stated it should alter the scale of pipe for a piece of pipeline in B.C. as a result of building difficulties drilling by means of exhausting rock.

If it isn’t granted the variance, the corporate warned, the undertaking’s completion — which was purported to happen in early 2024 — may very well be delayed by two years.

This report by The Canadian Press was first printed Dec. 18, 2023.

Share this text in your social community

Facebook
Twitter
Pinterest
WhatsApp
RELATED ARTICLES

LEAVE A REPLY

Please enter your comment!
Please enter your name here

Most Popular

Recent Comments