Indore (Madhya Pradesh): Visitors chaos continues unabated on the development websites of 4 flyovers within the metropolis and no reduction is in sight for the motorists for no less than the following six to eight months. This site visitors menace has now turn into a difficulty resulting in discomfort for individuals residing and commuting close to these development websites.

Situation of site visitors

Bhanwarkuwan Sq.

At Bhanwarkuan (Tantya Bheel) Sq. the site visitors coming from Rajeev Gandhi Sq. to Bhanwarkuan Sq. has been diverted in direction of the service highway resulting in a jam-like scenario on the highway adjoining to Gyani Ji Ka Dhaba. As the development work is occurring each side of the principle highway solely the BRTS lane is open for autos to go in direction of Vishnupuri facet from Bhanwarkuwan. This results in heavy site visitors congestion on the sq. and what provides to the congestion is the truth that many individuals don’t observe guidelines and bounce the pink gentle.

Khajrana Sq.

At Khajrana Sq. the scenario is analogous and the site visitors move on the sq. stays affected and site visitors jams are a each day prevalence. The service highway from Bengali Sq. in direction of Khajrana has been taken over for development work because of which individuals eager to take the left flip must halt on the sq..

Phooti Kothi Sq.

At Phooti Kothi Sq. too, the work of flyover leads to big site visitors jams. Folks dwelling in Sudama Nagar, Phooti Kothi and different close by areas must bear the agony of site visitors menace through the rush hours of the day.

Lavkush Sq.

At Lavkush Sq., individuals travelling in direction of Ujjain Street and Tremendous Hall must face a tricky time as not solely is the flyover being constructed however added to it’s the work of Metro Hall. Solely the service lane is open for autos which implies that there’s a big load of autos throughout rush hours of the day.

The flyover work is occurring at a quick tempo and we expect that by mid of subsequent yr, the work will likely be accomplished. The Khajrana Sq., Phootikothi Sq. and Bhanwarkuwan Sq. flyovers would be the first flyovers within the metropolis with a 45-metre span and uninterrupted area beneath it for clean site visitors move. Groups are working 24×7 in two shifts.

– IDA CEO RP Ahirwar

FLYOVERS SITUATION